Activity dates auto-adjust example

Let's say you have a listing with a listing date of January 1 and activity A set for January 10. Select the If listing date changes auto-adjust option for activity A. Now when you change the listing date to January 5, Activity A will auto-adjust to January 15.

Now let's say you had an activity B scheduled for a later date, and had selected the If preceding activity changes auto-adjust option, with activity A set as the preceding activity. Then activity B would also be updated to occur 10 days later than its original date.